1、電纜溝開挖施工方案Work Method of Cable Trench Excavation編 制:Compiled by:審 核:Reviewed by:2009年10月21日October 21,2009B301IB300 |A472 -rnri11 旬D TTrTTi iTIi 11 iTiil =Qmn 山 ll 山ll fllllHlHlllllllll WinnTTnTnTTTnWTTTTTTTTnTTTTTn435KV U/G Cable Main Routing.C581 South & A472.Line 135KV U/G Cable Main Routing.C581
2、North & A472.Line 3目錄Content一. 概況 OVERVIEW2工程概況 PROJECT OVERVIEW31.1 施工范圍 SCOPE OF WORK3編制依據(jù) COMPILATION BASIS4二. 施工工藝流程 CONSTRUCTION PROCESS:4前期準備PREPARATIONS44.1 技術(shù)準備 TECHNICAL PREPARATION4材料準備 MATERIAL PREPARATION54.2 主要機具準備 MAIN EQUIPMENTS PREPARATION5作業(yè)環(huán)境準備 OPERATING ENVIRONMENT PREPARATIONS5三.
3、 電纜溝施工 CABLE TRENCH CONSTRUCTION5電纜溝測量、定位 CABLE TRENCH MEASUREMENT AND POSITIONING. 55.1 電纜溝開挖 CABLE TRENCH EXCAVATION5質(zhì)量控制 QUALITY CONTROI76.1 電纜溝夕卜形尺寸允許偏差表ALLOWABLE DEVIATED EXTERNALDIMENSIONS OF CABLE TRENCH TABLE76.2應(yīng)注意的質(zhì)量問題QUALITY ISSUES7成品保護 FINISHED PROTECTION8四. 施工記錄 CONSTRUCTION OF RECORD8安
4、全生產(chǎn)、文明施工要求和措施SAFETY AND CIVILIZED CONSTRUCTIONREQUESTS AND MEASURES8附廠區(qū)電纜溝圖:ATTACHED: CABLE TRENCH DRAWING8一概況Overview工程概況 Project Overview項目名稱:本工程涉及三個變電站,分別是現(xiàn)有的220/35kV A472變電站、現(xiàn)有的35/10kV B301S變電站 以及新建的35/IOkVC581變電站,工作內(nèi)容為三個變電站之間和從三個變電站接至MV用戶的 電力電纜、控制電纜、接地電纜敷設(shè)所需電纜溝的開挖工程oThe project involves three s
5、ubstations, namely the existing 220/35kV A472 substation, the existing 35/10kV B301S the 35/10kV C581 substation and a new substation. This is the power, control and grounding cable trench excavation project among three substations and for MV users connected to the three substations.1.1 施工范圍 Scope o
6、f Worki) 由A472變電站引出3路35kV出線。其中:路引至B301S建筑(35/1 OkV變電站)原1#主變,原1#主變電纜將抽出,與新增4#主變連接: 另兩路引至35/1 OkV C581變電站I#主變和2#主變?;芈凡捎肍S-YJY-26/35kV-1 *300mm2單芯 電纜,直埋敷設(shè)。去C581的兩路35kV線路,敷設(shè)時沿不同路徑,以避免兩回線路同時受損。 Pull three 35V outgoings from A472 substation. Of which:The first outgoing is led to B30IS Building (35/1 OkV s
7、ubstation) (he original one # main transformer, pull the original one # main transformer cable out, and connect to the adding 4 # main transformer; the other two outgoings are led to 35/1 OkV C58I # I and substation 2 # main transformer. Use FS-YJY-26/35kV-1 * 300mm2 single-core cables for Loop and
8、buried pulling. Two 35kV lines to C581 arc laid along different paths to avoid damage of the two loops.2) 由B30IS變電站引出7路l()kV出線。全部引至B399中心制冷站。回路采用IOkV截面為95 mm2 的三芯鎧裝電纜,由B301S南面現(xiàn)有的電纜井引出直埋至裝置。Pull 7 IOkV outgoings from B301S substation to B399ccntral refrigeration station. Loop uses IOkV thrce-corc arm
9、ored cable with cross-section 95mm2 and pull out from the existing cable well in the south of B301S then buried lay to the device.3) 由C581引出10路IOkV線路,分別為A507的四臺變壓器,B551的兩臺變壓器,B553TDA裝 置氫氣壓縮機2臺,C521鹽酸裝置氯氣壓縮機1臺,鹽酸壓縮機1臺提供電源。其中,變壓器 回路采用IOkV截面為185mm2的三芯鎧裝電纜,馬達回路采用IOkV截面為95mm2的三芯鎧裝 電纜。以上電纜線路均沿規(guī)劃路徑埋地敷設(shè)。10
10、IOkV lines led from C58I are used co supply power to A507s four transformers, B551 two transformers, B553TDA 2 sets of hydrogen compressor unit, C52I hydrochloric acid chlorine gas compressor unit, and hydrochloric acid compressor unit respectively. Among them, transformer circuit uses x 3-core armo
11、red cable with IOkV cross-section 185mni2, motor circuit uses thrce-corc armored cable with IOkV cross-section 95nim2. All cable lines will be laid underground along the planning path.4) 接地電纜回路:Ground cable loop:從A472敷設(shè)一根95mm2裸銅線去C581,同時從C58I敷設(shè)四根95mm2裸銅線,分別引至B551、 A507、B553和C521,作等電位聯(lián)結(jié)。以上電纜線路均沿規(guī)劃路徑埋
12、地敷設(shè)。Lay a 95mm2 bare copper wire to C58! from A472. Meanwhile lay four bare copper wires to B551, A507, B553 and C521 for equipotential bonding. All cable lines will be laid underground along (he planning path.5) 本工程電纜溝走向如下:The cable trench directions are as follows:電纜溝南線為A472至C581,全長約850米,根據(jù)K-K斷面圖:
13、開挖深度為I米,溝槽底寬().6 米,溝槽面寬約 1.1 米。 Cable trench south line is from A472 to C581 about 850 meters long. According to KK sectional drawing, excavation depth is of 1 meter with trench bottom width 0.6 in and face width 1.1 m.電纜溝北線為A472至C58I和B301,其中共線約220米,根據(jù)A-A斷面圖有:開挖深度為1 米,溝槽底寬 1 米,溝槽面寬約 1.5 米;Cable tren
14、ch north line is from A472 to C581 and B301 and the col linear is about 220 meters. According to AA sectional drawing, excavation depth is 1 meter trench wilh trench bottom width 1 m and face width 1.5 m.至C581支線約430米,根據(jù)E-E斷面圖有:開挖深度為I米,溝槽底寬0.6米,溝槽面寬約1.1 米;至B301支線約300米,根據(jù)B-B斷面圖有:開挖深度為1米,溝槽底寬0.6米,溝槽面寬
15、約 1.1 米。The sub-line the C581 is about 430 meters. According to EE sectional drawing excavation depth is 1 meter trench with trench bottom width 1 m and face width 1.1 m. The sub-line to B301thc is about 300 meters. According to BB sectional drawing , excavation depth is 1 meter trench with trench b
16、ottom width 1 m and face width 1.1 in.二. 編制依據(jù) Compilation Basis1)根據(jù)電氣包(中壓部分)招標文件及招標圖紙編制而成。According to Electric package (MV) the tender and tender drawings.2)在充分研究工程的客觀情況和施工特點,結(jié)合我公司類似工程施工經(jīng)驗的基礎(chǔ)上編制Wo Based on full study on construction characteristics and objective situation and combined with similar
- 1.請仔細閱讀文檔,確保文檔完整性,對于不預(yù)覽、不比對內(nèi)容而直接下載帶來的問題本站不予受理。
- 2.下載的文檔,不會出現(xiàn)我們的網(wǎng)址水印。
- 3、該文檔所得收入(下載+內(nèi)容+預(yù)覽)歸上傳者、原創(chuàng)作者;如果您是本文檔原作者,請點此認領(lǐng)!既往收益都歸您。
下載文檔到電腦,查找使用更方便
10 積分
下載 | 加入VIP,下載共享資源 |
- 配套講稿:
如PPT文件的首頁顯示word圖標,表示該PPT已包含配套word講稿。雙擊word圖標可打開word文檔。
- 特殊限制:
部分文檔作品中含有的國旗、國徽等圖片,僅作為作品整體效果示例展示,禁止商用。設(shè)計者僅對作品中獨創(chuàng)性部分享有著作權(quán)。
- 關(guān) 鍵 詞:
- 室外 電纜溝 施工 方案 中英文